January-February 2008

Slope Stabilization in an Oilfield in Arctic Alaska

Fighting flooding and erosion on the tundra

Article Tools

Create a Link to this Article

By Timothy C Cater, M. Torre Jorgenson, Susan C. Bishop, Caryn L Rea

Comments

The Arctic Coastal Plain of northern Alaska is a vast area of treeless tundra, with low relief and numerous lakes and rivers flowing into the Beaufort Sea. This area, commonly referred to as the North Slope, has supplied a substantial portion of the oil used in the United States since production began in 1977. The Alpine oilfield (70°20’N, 150°56’W) began producing oil in 2000 and was the first field to be developed within the delta of the Colville River, one of the largest rivers on the North Slope (Figure 1). Flooding and erosion are primary environmental concerns that prompted the development of innovative engineering techniques to stabilize the Alpine oilfield infrastructure. As of 2004, infield facilities included approximately 8 miles of gravel sideslopes along roads, pads, and an airstrip. In this article, we describe the combination of physical armoring and biotechnical stabilization methods used to stabilize these slopes. To the best of our knowledge, these biotechnical stabilization techniques have not previously been used on a large scale in the Arctic.

Background
Perennially frozen ground, or permafrost, is a primary factor affecting the design of oilfields in the Arctic. Only the top 1 to 3 feet of soil thaws during the short, cool arctic summer, while the deeper soil remains frozen and may contain a substantial amount of ice. To conduct oilfield activities, it is necessary to insulate the permafrost, to minimize thawing and subsidence (thermokarst) resulting from melting ice and subsequent loss of soil volume. Thus, facilities and vehicle traffic typically operate on roads, pads, and airstrips that are constructed of gravel fill about 6 feet thick. The thick fill minimizes heat transfer to the underlying soil, thereby maintaining a stable working surface. In the Alpine oilfield, however, it was necessary to use gravel fill as thick as 10 feet, to elevate the facilities sufficiently above spring floodwaters. To minimize the footprint of the facilities and reduce the quantity of gravel required, relatively steep slope angles (approximately 2:1) were incorporated into the design (Figure 2).

Advertisement

Placing thick gravel fill structures in the delta was expected to affect water flows under certain conditions. Hydrological modeling indicated that floodwater velocities sufficient to cause some erosion of the steep gravel slopes would likely occur in some years. The largest flood event each year typically occurs during spring breakup in late May and early June (Figure 3). During the spring flood in 1993, which was considered a moderate flood event with a return period of five years, the peak discharge was 379,000 cubic feet per second (cfs), and water covered 69% of the area where the Alpine facilities were to be developed. Simulation modeling indicated that during a 200-year flood event, the peak discharge could be as high as 1,000,000 cfs, resulting in flooding of nearly the entire area.

Concerns about flood erosion were addressed partly by siting most of the facilities on higher portions of the floodplain, where flooding is less frequent and flow velocities are less extreme. For example, the elevation at the toe of most of the gravel sideslopes is at the maximum elevation that floodwaters are expected to reach during a 50-year flood. To protect against the erosion of the sideslopes during flooding, physical armoring and biotechnical stabilization techniques were applied. These techniques were approved in the permit issued by the US Army Corps of Engineers for the development of the Alpine oilfield. Next Page >

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Erosion Control E-mail Updates!

Get weekly news and updates through our Erosion Control e-mail newsletter!