January-February 2009

Channel Protection Measures

Hard- and soft-armor options

Article Tools

Create a Link to this Article

Photo: Bethlehem Precast

By Steve Goldberg

1 Comments


Cable Concrete consists of pyramidal-shaped concrete blocks interwoven with stainless steel cable and underlaid with an erosion-minimizing geotextile fabric. It allows infiltration between the blocks and can be overseeded if desired.

Faust explains that the purpose of the Frost Hollow channel is both to move stormwater runoff and to allow infiltration into the ground. “The benefit of the articulated blocks is that grass grows over and between the blocks, causing a filtering benefit as well as a better aesthetic appearance,” he says. “Within a relatively short period of time the area looks very natural. In this specific project, we did not overseed with grass but let nature take its course. Over time, the area silts up and vegetates naturally. Now, a year and a half after the project’s completion, it looks quite natural, and before long, you won’t be able to see the articulated blocks at all. This vegetation, of course, slows down the velocity of stormwater, and you get infiltration, which is what you want.”

The Frost Hollow project was completed in September 2007, and Faust notes that engineers involved with the effort are quite pleased. A total of 362 eight- by 16-foot Cable Concrete mats were used, along with 181 four- by 16-foot mats, totaling nearly 58,000 square feet. The channel has been successfully widened, erosion appears to have been arrested, and the channel treatments have performed exactly as desired. There have been several major storm events since the installation, with no reports of any new basement flooding.

Antelope Creek
Antelope Creek is a small stream running through Lincoln, NE. As noted in the Antelope Valley Study issued by the city of Lincoln, the creek meanders in an open channel underneath a number of street bridges and through many residential and business neighborhoods until it moves underground into an enclosed conduit. From there, it travels underneath several buildings, re-emerging aboveground a couple of blocks later. The final leg of the creek again meanders in an open channel underneath more street bridges, passes through the campus of the University of Nebraska, travels underneath railroad tracks, and finally empties into Salt Creek.

“Because of increased runoff caused by urban development in the lower reaches of the Antelope Creek basin,” states the Antelope Valley Study, “only a four-year or smaller storm is calculated by the engineers to fit into the conduit, and any larger storm would exceed the conduit and cause the excess water to travel overland, flooding many … neighborhood streets and properties.”

Furthermore, a number of street bridges over the creek are so small and low that as the creek rises, these bridges act as small dams, contributing to the flooding of nearby properties. The study estimates that in a 100-year flood event, some areas would be under up to 6 feet of floodwater. In an analysis by the US Army Corps of Engineers, it was determined that even an 8-year flood would result in widespread damage.

Over the past century, Antelope Creek has flooded numerous times, most severely in 1908, when 10 lives were lost.

The goal of the Antelope Creek flood control project is to reduce the estimated annual flood damage by 80%, as well as to confine the 100-year storm event within the channel banks.

Wayne Wendel of Contech Construction Products in Lincoln notes that erosion concerns existed as well, but because of increased surface runoff caused by the impervious surfaces from city development, continual flooding was the primary issue with Antelope Creek.

Wendel explains that the Joint Antelope Valley Authority (JAVA) “pushed for a ‘green’ solution,” desiring “a channel that would look natural, yet have the ability to withstand the events that occur here.”

JAVA has produced a 20-year development plan for the creek basin, incorporating work on three channel reaches. “I have been involved with all of them from the very beginning,” Wendel says. “Presentations on ArmorFlex”—an articulated concrete block revetment system—“and erosion control TRMs [turf reinforcement mats] were given to JAVA prior to the design being completed. We then worked with the corps and the engineer [Olsson Associates of Lincoln] to size the ArmorFlex and TRMs. The project is ongoing. Hawkins Construction Company of Omaha has been the contractor that has performed the work up until the most recent bid, which was just awarded to Park Construction out of Minnesota. We have approximately 100,000 square feet of ArmorFlex to supply for the phase that just bid.”

Continuing downtown development increases the problems faced from channel flooding. “Antelope Creek is the main drainage channel of the city, and with the development of recent years, it had become undersized,” stresses Wendel.

He explains that curative options were somewhat limited. “There was no soft armor available—and still isn’t—that can withstand the shear forces and velocities present in the channel. I would estimate that any hard-armor solution is going to cost approximately 2.5 to 4 times what a soft-armor solution would, the caveat being that most times ArmorFlex is being considered as a design solution, there simply is no soft-armor solution.”

The Antelope Creek flood control project is still ongoing, but Wendel says that the creek has been treated to allow silt to settle out, and the ArmorFlex used is designed to allow the establishment of vegetation, producing some level of water treatment. However, “the main goal was to move water.”

To date, Wendel says, “The reaction has been very positive from the business owners and public officials. There was some resistance to the project from some homeowners and business owners that had to give up property. However, that stemmed from the road and bridge projects that went along with the channel improvements. It was the new road and bridges that caused most of the negative reaction because of the eminent domain issues and establishment of easements. Like many things, the public doesn’t like the delays and inconvenience during construction, but will be very pleased upon completion, and are already pleased with the performance of the channel.”

Neabsco Creek Channel
Neabsco Creek is a tributary of the lower tidal segment of the Potomac River located in eastern Prince William County, VA. Alan Dinges, assistant area manager for Maccaferri Inc., says, “The creek has served as a vital waterway for trade and commerce in northern Virginia since the eighteenth century. The EPA Office of Water has identified the Neabsco Creek watershed as an ‘area of significant habitat degradation’ due to a loss of natural land cover and stormwater management facilities designed without consideration for environmental conditions.”

Because of its sandy soil and a steep slope, a hillside drainage channel emptying into Neabsco Creek was suffering severe erosion. The county hired engineering firm R. A. Smith National Inc. and specified that gabions (essentially rock-filled baskets) should be used to stabilize the drainage channel. This firm contracted with Maccaferri in Williamsport, MD, for design work.

According to Maccaferri’s Larry Bakner, “Maccaferri provided an initial design for consideration. The project went through numerous revisions, and a final design was decided on in the spring of 2008. Upstream development was the reason for concern on this project. A large commercial development, 650,000 square feet, was to have three outfall areas with 48-inch and 54-inch concrete pipes. The design flows were 120 and 160 cubic feet per second for a 100-year event, with velocities around 10 feet per second.”

Bakner explains the primary goal of the work: “The channel was designed to move the water from the commercial site into an existing stream, and also to dissipate velocities. An inspector was continually onsite during construction to monitor the water quality in the stream.”

Dinges adds, “This project has very high visibility, and this is the reason it was monitored so closely.”

Advertisement

As with the Antelope Creek project, options were limited, especially because the county had specified the use of gabions to repair the channel. “A soft-armor solution was not considered,” Bakner says. “Gabions and riprap were both considered as solutions, but due to the steep slope and water velocities, gabions were chosen as the best solution.”

The gabion installation was completed shortly after the final design approval. It consists of approximately 1,400 cubic yards of galvanized gabions, placed on top of Maccaferri’s MacTex MX-275 nonwoven geotextile material. The resulting gabion structure is quite striking and appealing to the eye, in stark contrast to the initial appearance of the eroded channel. Bakner notes that, not surprisingly, the engineers were quite pleased with the results.  

Author's Bio: Steve Goldberg is a writer in St. Louis, MO.

What Do You Think?

Post a Comment

Cdon

December 16th, 2008 3:43 PM PT

I have a problem with the context of the below statement. He explains that curative options were somewhat limited. "There was no soft armor available-and still isn't-that can withstand the shear forces and velocities present in the channel. I would estimate that any hard-armor solution is going to cost approximately 2.5 to 4 times what a soft-armor solution would, the caveat being that most times ArmorFlex is being considered as a design solution, there simply is no soft-armor solution." www.scourstop.com will show you the soft armor which has been proven to handle the flows mentioned. Used on multiple projects with Army Corps involement on waterways such as the Mississippi. Proven via colorado state to velocites up to 21.5 f/s. While protecting properly, enabling all of the positives mentioned in the first part of the article. I would like to see a follow up article involving the actuall capabilities of the soft armor protection authored. Corydon Coppola

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Erosion Control E-mail Updates!

Get weekly news and updates through our Erosion Control e-mail newsletter!