March-April 2008

  • 1
  • 2

A Test of Strength

Geosynthetic materials for erosion control applications

Article Tools

Create a Link to this Article

Additional Article Content

By Carol Brzozowski

Comments

Very few weather events can test the strength of geosynthetics as a hurricane.

That’s exactly what happened last August 19 when Hurricane Dean—which had grown to be a Category 4 hurricane—pounded the southern coast of Jamaica with wind speeds of up to 155 miles per hour, killing three people and causing about $5 billion in damage.

Photo: GeoProducts
Photo: GeoProducts
Photo: GeoProducts
Nonwoven geotextile and Envirogrid lined earthen pond structures at a wastewater treatment plant in Jamaica.
The structure withstood a Category 4 hurricane in 2007.

Employees of In-Line Plastics, a manufacturer and installer of polyethylene geomembranes for GeoProducts, had attained 95% completion of a geosynthetic project at the Soapberry Wastewater Treatment Plant near Kingston, Jamaica, when the hurricane hit.

In-Line Plastics produces low-density and high-density polyethylene (HDPE) in measurements of 12, 20, 30, and 40 mils. Crews travel worldwide for installation, or panels are prefabricated and shipped to end users.

In Jamaica, the installation suffered no damage as a result of the hurricane, although the entire installation crew could not be demobilized to fly back to the United States, with two remaining behind to ride out the hurricane.
In the four months leading up to the storm, the crews had been working at the Soapberry plant, Kingston’s first wastewater treatment plant.

“In the past, all of the sewer disposal was going directly into the ocean,” says the company’s Al Florez. “There is a set of ponds for the wastewater treatment plant. The requirement the engineer had was that they have enough clay materials for the bottom of these ponds, but they did not have enough for berms that they were creating that would separate one pond from the one adjacent to it.

“There were two sets of dikes for ponds that were next to each other. We lined the dikes for the slopes with a 40-mil high-density polyethylene and then used a 6-ounce nonwoven geotextile and then 3-inch Envirogrid [a three-dimensional HDPE system] that was filled with concrete.

“The reason for the liner was to impede the water from filtrating through the soil and deteriorating those berms for the dikes,” says Florez. “The Envirogrid filled with concrete was to protect against any type of impact from hurricanes.”

The original design had called for earthen dikes and slopes and then for the Envirogrid filled with concrete or 60-mil liner on top of that, notes Florez. “We reversed the order by allowing the concrete structure to be on top,” he says. “Being able to use material that was not so thick—dropping it from a 60-mil to a 40-mil—saved the project owner 50% of the cost of the liner alone.”

The initial concern about water penetrating the berms was of high priority, and the liner being in place limited the ways that concrete could be poured on top of that liner, because the typical situation was to create wooden forms, says Florez. “The forms have to be anchored to the ground below, and when you anchor it, you would then perforate the liner,” he says. “With the Envirogrid material, you expand the cells on top of the geotextile, which is on top of the liner, without any need of penetrating the geomembrane whatsoever.”

This type of application is becoming more common with engineers and those owning ponds who want to protect pond perimeters, says Florez. “Sometimes it’s to protect it from puncturing, and at other times it’s so it is aesthetically pleasing,” he says.

Photo: GeoProducts
Workers place the three-dimensional grid at the Soapberry plant.

Ponds can look “ugly,” Florez notes, “because when the water goes down, you see the black liner. But by laying the Envirogrid on top of it and filling it with soil, you can vegetate it so the pond looks natural.

“In Jamaica, [the Envirogrid] was used to protect the geomembrane, and the best way to protect it was with concrete, but the standard way of pouring concrete would have not done the job. It would have damaged the liner, so the use of Envirogrid allowed them to pour the concrete directly on top of the geomembrane on the geotextile without any use of stakes.”

Expansion in Edmonton
The city of Edmonton in Alberta, Canada, has been expanding rapidly to the south and west. Two years ago, the only freeway to transport traffic through the area was the Whitemud Freeway.

But the freeway was constantly congested during rush hour, and it was evident that a new roadway had to be constructed to reduce the inevitable gridlock that would occur with Edmonton’s continued population boom.

The result was the construction of the Anthony Henday Drive, also known as Highway 216, which traverses the southern and western boundaries of Edmonton.

Its construction, however, crossed the North Saskatchewan River and several creeks. That, coupled with steep slopes, called for an erosion control approach that would protect the adjacent waters.

The original design featured an arch structure with wing walls and a tiered concrete-faced wall system. The plans were changed to incorporate a geogrid-reinforced soil slope (RSS) system.

Photo: GeoProducts
Aerial view of the Soapberry plant

That system was provided by the Layfield Group. Using LP 120T PVC-coated polyester geogrid, the company worked with the prime contractor and geotechnical engineer to complete a final design. The slope was completed in early 2005.

“The main issue was to provide slope reinforcement, erosion protection, and long-term stability to a steep slope,” says Robin Tweedie, a principal with Thurber Engineering, the geotechnical engineering firm.

“The contractor had looked at several alternate proposals—including a reinforced earth–type scenario—and eventually he decided this one met his requirements best, so we were involved in the geotechnical design of it.”

The slope started at about 1.2:1 and, moving away from the arch, eventually became a general slope of 3:1. The steep area that required slope stabilization was close to the arch and adjacent to Whitemud Creek.

Dallas Lindskoog, the project manager on behalf of Kiewit Management, the prime contractor, notes that there was not a large area in which to work.

Advertisement

Obviously a 1:1 slope doesn’t stand up on its own, so we had to find some way of reinforcing it. That’s why we went to the geogrid,” he says.

Other materials provided by the Layfield Group include the LP 30T polyester geogrid, 4-inch geocell, and PP5-10 turf reinforcement mat (TRM).  “The only other options were retaining wall structures, which were not feasible at the time,” says Lindskoog. Next Page >

  • 1
  • 2

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Erosion Control E-mail Updates!

Get weekly news and updates through our Erosion Control e-mail newsletter!