November-December 2000

Effective Erosion Control for a Highway Construction Project

The Goshen to Pleasant construction project is an example of a well-planned and well-implemented erosion and sediment control plan.

Article Tools

Create a Link to this Article

By Frannie Brindle

Comments


Permanent seeding was done on three occasions throughout the project, although the majority occurred in late September and early October 1999. The seeding and mulching was subcontracted to Anderson Construction. The cut slopes were shaped with a slopeboard, a wing out from the bulldozer with a hydraulic adjustment. During the first pass a cut was made into the slope face with the dozer arm raised. A second pass followed in which the arm was lowered to serrate the soil surface. The result was a surface roughening of about 30 in., with grooves running parallel with the slope contours.

Upon site review it appeared that the erosion from the cut slopes was well controlled by the combination of good surface treatment and excellent vegetation establishment. At the time of the site visit, 70% of the work had been completed, including permanent grading and vegetation establishment, curb and storm drain in the urban section, and half of the retaining wall construction completed. Remaining work includes shoulder widening and paving. Completion is expected in fall 2000.

No matter how well a highway construction project is run, problems will occur. According to the contractor, traffic was tough to deal with and the contractor was not allowed to constrict traffic between the hours of 7 a.m. and 9 a.m. and 2 p.m. through 6 p.m. To keep the project on schedule, the contractor worked around the clock for six weeks. Another problem was that they had to waste a majority of the soils resulting from the cuts and could not use it for fill, as it was too wet. This resulted in disposal of about 225,000 yd.3 of material.

Advertisement

The total cost of the construction project is projected to be $8.9 million. The contractor costs for erosion control is $113,292. The Erosion and Sediment Control Plan (ESCP) bid estimate was $132,591, or less than 1% of the total project cost. ODOT’s erosion control team in the Geo-Hydro Section developed the plan. The ESCP was developed for a worst-case scenario as the project schedule projected excavation work to occur during the rainy winter season. The contract for construction was let in January 1999. The plan included supported and unsupported sediment fence, straw-bale sediment barriers, inlet protection, aggregate check dams, aggregate construction entrances, temporary slope drains, temporary sediment traps, diversion dike swales, and permanent seeding and mulching.

The revised plan differed from the created plan. The plan developed by ODOT called for almost 6,500 ft. of diversion dike at the toe of fills. The idea was to save on the use of sediment fence by creating a small dike at the toe and seed the berm so that it would become stable. Sediment-laden water could collect in the swale, where it could slow the velocity and settle out soil particles. The revised erosion control plan submitted by the contractor did not use the diversion dike swale approach, as drainage on the project was revisited and drainage ditches were created at the toe of fills instead. Next Page >

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get Erosion Control E-mail Updates!

Get weekly news and updates through our Erosion Control e-mail newsletter!